Impatience
solemio
Registered Users Posts: 16 ✭
How long did it take from the point of signing your contract for a solar PV system to actual permission to use? We signed July 13th.
Comments
-
Re: Impatience
For me, almost 3 months... Big part of the delay was a shortage of UV rated cable (3 years ago, wire and panels were in short supply). The building department, solar panels, and other parts came on time...
Maybe a week or so lost in labor scheduling by the contractor. Utility came out within a week to install meter (and promptly overcharged me $200 for 2 weeks of electricity when my monthly electric bill--before solar--had been $30--make sure you write down your meter reading before they change it out--our confusion was caused because when our system passed inspection, it was left on and the meter spun backwards while before the utility had set up our account for net metering and really confused the billing computer).
If everything was available, 3-6 weeks would be reasonable (from my limited experience). In states with rebates--you might have another 2-4 weeks of paperwork processing delay.
-BillNear San Francisco California: 3.5kWatt Grid Tied Solar power system+small backup genset -
Re: Time Table for SolarHow long did it take from the point of signing your contract for a solar PV system to actual permission to use? We signed July 13th.
Hello out there, anyone! -
Re: Impatience
I told you mine... How long did they tell you it would take? Did they break it out into stages (rebates, permits, installation, inspection, utility approval/meter change)?
-BillNear San Francisco California: 3.5kWatt Grid Tied Solar power system+small backup genset -
Re: Impatience
3 months...some installers in Austin are quoting 2+ month waiting periods to begin the install. -
Re: Impatience
The installs are pretty quick. One person doing the conduit. Two people installing the rails and panels... Took more people and a longer time to strip and re-roof my asphalt shingle roof.
-BillNear San Francisco California: 3.5kWatt Grid Tied Solar power system+small backup genset -
Re: Impatience
We received a call already from PG&E regarding the new meter but we're still awaiting permits for the install. -
Re: Impatience
Probably depends a lot on where you are. Here in New York state, I signed my contract the last week of March and I am still waiting for state approval (NYSERDA) with no target date. (When I contacted NYSERDA a couple of weeks ago they just said that they appreciate my patience!) -
Re: ImpatienceProbably depends a lot on where you are. Here in New York state, I signed my contract the last week of March and I am still waiting for state approval (NYSERDA) with no target date. (When I contacted NYSERDA a couple of weeks ago they just said that they appreciate my patience!)
Are they so busy with the flood of solar installations or just a huge bureaucracy? -
Re: ImpatienceAre they so busy with the flood of solar installations or just a huge bureaucracy?
I suspect bureaucracy, but I really don't know for sure. Maybe it is related to the state's financial woes. Their website states that they will process applications within 30 business days, but that obviously is not happening. -
Re: ImpatienceI suspect bureaucracy, but I really don't know for sure. Maybe it is related to the states financial woes. Their website states that they will process applications within 30 business days, but that obviously is not happening.
Good news! New York State (NYSERDA) finally got around to approving my application (as of 8/21/2009)! Installation is now tentatively scheduled for the week of 9/28/2009. It might take a month after that for our electric company to give approval to go on-line. Patience is definitely required! -
Re: ImpatienceGood news! New York State (NYSERDA) finally got around to approving my application (as of 8/21/2009)! Installation is now tentatively scheduled for the week of 9/28/2009. It might take a month after that for our electric company to give approval to go on-line. Patience is definitely required!
That's great! With any luck, you should be back-feeding the grid just in time for one of NY's famous winters full of sunless skies. Do you live anyplace near Watertown, where the daily lake-effect snowfall is measured in feet?
Oh well, think how nice it will be next summer. -
Re: Impatience
We just got word that we are tentatively scheduled for September 23-27th... a little over two months after signing the contract. -
Re: Impatience
must be some kind of common denominator with the end of september. -
Re: ImpatienceCariboocoot wrote: »That's great! With any luck, you should be back-feeding the grid just in time for one of NY's famous winters full of sunless skies. Do you live anyplace near Watertown, where the daily lake-effect snowfall is measured in feet?
Oh well, think how nice it will be next summer.
Fortunately I am about an hour and a half south of Watertown, so I am not in the daily lake-effect snow machine area. It is a bit sad that I won't see too much production for a while though. -
Re: Impatience
OK, I can finally give my complete time line for my system in upstate New York:
1) Signed the contract and wrote the first check: 3/26/2009
2) NYSERDA received the incentive application from the installer: 4/20/2009
3) NYSERDA finally got around to giving approval: 8/21/2009
4) System installation: 3 days, 9/29/2009-10/1/2009
5) Electrical inspection visit: 10/5/2009
6) NYSEG replaced their meter: 10/19/2009
7) NYSEG conducted final interconnection verification test: 10/23/2009
8) System on-line! 10/23/2009
So, it took almost exactly 7 months from contract signing until the system was on-line. Of that, installation took 3 days. The rest of the time was waiting. (It was a good thing there were never any issues!) -
Re: Impatience
congrats on finally getting it. let us know how well it does for you too. -
Re: ImpatienceOK, I can finally give my complete time line for my system in upstate New York:
1) Signed the contract and wrote the first check: 3/26/2009
2) NYSERDA received the incentive application from the installer: 4/20/2009
3) NYSERDA finally got around to giving approval: 8/21/2009
4) System installation: 3 days, 9/29/2009-10/1/2009
5) Electrical inspection visit: 10/5/2009
6) NYSEG replaced their meter: 10/19/2009
7) NYSEG conducted final interconnection verification test: 10/23/2009
8) System on-line! 10/23/2009
So, it took almost exactly 7 months from contract signing until the system was on-line. Of that, installation took 3 days. The rest of the time was waiting. (It was a good thing there were never any issues!)
Since my system has been online for 1 year as of today, time for a performance report:
System: (20) Sunpower SPR225 panels, Sunpower 5000m (rebranded SMA Sunnyboy 5000us) inverter, roof mounted at 25 degree roof angle, facing south.
Production: For the year, 5427 kWh (14.9 kWh/day average). (PVWATTS prediction 5051 kWh).Best month: July 2010: 714 kWhWorst month: December 2009: 177 kWh
Total consumption for the year: 5103 kWh (13.9 kWh/day average), so my system produced more than I used for the year.:D -
Re: Impatience
time flies doesn't it? thanks for the update on your system performance and i'm glad it's working good for you.
Categories
- All Categories
- 222 Forum & Website
- 130 Solar Forum News and Announcements
- 1.3K Solar News, Reviews, & Product Announcements
- 192 Solar Information links & sources, event announcements
- 888 Solar Product Reviews & Opinions
- 254 Solar Skeptics, Hype, & Scams Corner
- 22.4K Solar Electric Power, Wind Power & Balance of System
- 3.5K General Solar Power Topics
- 6.7K Solar Beginners Corner
- 1K PV Installers Forum - NEC, Wiring, Installation
- 2K Advanced Solar Electric Technical Forum
- 5.5K Off Grid Solar & Battery Systems
- 426 Caravan, Recreational Vehicle, and Marine Power Systems
- 1.1K Grid Tie and Grid Interactive Systems
- 651 Solar Water Pumping
- 815 Wind Power Generation
- 624 Energy Use & Conservation
- 611 Discussion Forums/Café
- 304 In the Weeds--Member's Choice
- 75 Construction
- 124 New Battery Technologies
- 108 Old Battery Tech Discussions
- 3.8K Solar News - Automatic Feed
- 3.8K Solar Energy News RSS Feed