I used an online company to do my solar site plan packet for my local Building & Safety Department. They have done some calculations that look a little off to me. If anyone could help out with correct values, I would really appreciate it, the N.E.C. Tables 310 series are just confusing me. The image is from combiner boxes at array to inverters. It has (4) current carrying conductors @ 4AWG. ISC=9.11. There are 8 strings of 3 modules coming from each combiner box. I don't believe it has a bearing on the calculations, but I'll be using Schedule 40 1-1/4" PVC conduit. If more details are needed, let me know.
Thank you for your consideration.
Thank you for your consideration.
Comments
-
"There are 8 strings of 3 modules coming from each combiner box".
To clarify - you have a total of 16 strings (16x3=48 panel)? These go two 2 combiner boxes, 8 strings per box. From each box they propose a pair of 4ga wires to charge controller/inverter(s).
The required ampacity line appears to be 4 strings per box, not 8 (9.11x1.25x1.25=56.94), which it seems to me would be for 24 panels, 8 strings total split 4 per box. How many panels are you getting?
As well as meeting code, voltage drop may be a factor if going any distance from array combiners to controller.Off-grid.
Main daytime system ~4kw panels into 2xMNClassic150 370ah 48v bank 2xOutback 3548 inverter 120v + 240v autotransformer
Night system ~1kw panels into 1xMNClassic150 700ah 12v bank morningstar 300w inverter -
djohnyvonne said:ISC=9.11. There are 8 strings of 3 modules coming from each combiner box.
-
Estragon,
my system will have 48 panels.
2-MNPV12 combiner boxes
2-GS8048A inverters
2-GSLC load centers
4-flexmax FM80 charge controllers -
Putting panels in series and using a pair of 600V 80A charge controllers could simplify things a lot. And save on wire cost.
Powerfab top of pole PV mount | Listeroid 6/1 w/st5 gen head | XW6048 inverter/chgr | Iota 48V/15A charger | Morningstar 60A MPPT | 48V, 800A NiFe Battery (in series)| 15, Evergreen 205w "12V" PV array on pole | Midnight ePanel | Grundfos 10 SO5-9 with 3 wire Franklin Electric motor (1/2hp 240V 1ph ) on a timer for 3 hr noontime run - Runs off PV ||
|| Midnight Classic 200 | 10, Evergreen 200w in a 160VOC array ||
|| VEC1093 12V Charger | Maha C401 aa/aaa Charger | SureSine | Sunsaver MPPT 15A
solar: http://tinyurl.com/LMR-Solar
gen: http://tinyurl.com/LMR-Lister , -
In that case it appears the wiring will be inadequate, so heavier and/or more wires, and/or more conduit to reduce fill factor derating, and/or consider high voltage controllers.Off-grid.
Main daytime system ~4kw panels into 2xMNClassic150 370ah 48v bank 2xOutback 3548 inverter 120v + 240v autotransformer
Night system ~1kw panels into 1xMNClassic150 700ah 12v bank morningstar 300w inverter
Categories
- All Categories
- 222 Forum & Website
- 130 Solar Forum News and Announcements
- 1.3K Solar News, Reviews, & Product Announcements
- 192 Solar Information links & sources, event announcements
- 888 Solar Product Reviews & Opinions
- 254 Solar Skeptics, Hype, & Scams Corner
- 22.4K Solar Electric Power, Wind Power & Balance of System
- 3.5K General Solar Power Topics
- 6.7K Solar Beginners Corner
- 1K PV Installers Forum - NEC, Wiring, Installation
- 2K Advanced Solar Electric Technical Forum
- 5.5K Off Grid Solar & Battery Systems
- 425 Caravan, Recreational Vehicle, and Marine Power Systems
- 1.1K Grid Tie and Grid Interactive Systems
- 651 Solar Water Pumping
- 815 Wind Power Generation
- 624 Energy Use & Conservation
- 611 Discussion Forums/Café
- 304 In the Weeds--Member's Choice
- 75 Construction
- 124 New Battery Technologies
- 108 Old Battery Tech Discussions
- 3.8K Solar News - Automatic Feed
- 3.8K Solar Energy News RSS Feed